Concrete for Retaining Wall Footings: Volume, Grade and Access Guide

Most residential retaining wall footings need 1–3 m³ of ready-mix. Work it out as length × width × depth from the engineer's drawing, add 10%, and order the specified grade, usually N25 or N32. On tight sites, access decides the price: truck size, pump and short-load fees.

Concrete truck chuting ready-mix into a reinforced strip footing for a retaining wall, with starter bars set along a cut bank
Foucauld Dalle, Founder of MixHubUpdated 30 September 2026

Quick Answer

A typical backyard retaining wall in Sydney, whether it is a 10–15 m block wall along a boundary or a sleeper wall on steel posts, uses between 1 m³ and 3 m³ of concrete in the footing. That puts most of these jobs in small-load territory, where the delivered price per cubic metre can be 15–73% above the headline rate because of short-load fees. That is too much for bags and too little for a standard truck to be cheap.

Three decisions set the cost and the risk of the pour:

  1. Quantity. Order what the drawing needs plus a sensible allowance. Running short mid-pour leaves a cold joint in a structural footing.
  2. Specification. Order the grade, slump and aggregate the engineer specified. Don't swap in a cheaper mix on the day.
  3. Access. Retaining walls usually sit at the back or low side of a sloping block. Whether a standard truck, a mini-mix truck, a pump or a barrow crew gets the concrete there often moves the job cost more than the grade does.

How Much Concrete Does a Retaining Wall Footing Need?

Retaining walls use one of two footing types. Your engineer's drawing will show which one, with dimensions in millimetres. Sleeper-wall piers are commonly 300–450 mm in diameter, and as a rough guide they go about as deep as the wall is high. The drawing still decides.

Footing typeTypical wallVolume formula
Strip footingBesser block, brick or concrete walllength (m) × width (m) × depth (m)
Bored piersTimber or concrete sleeper wall on steel postsπ × (diameter ÷ 2)² × depth (m) × number of piers

Convert millimetres to metres before multiplying: 600 mm is 0.6 m. Then add a waste allowance. For footings, 10% is a sensible default because trenches are rarely dug perfectly square, and soft or crumbly trench walls take more concrete than the drawing shows. Use 5% for a clean, formed footing and 15% for rough or sandy excavation.

Round up to the next 0.2 m³, because most Sydney plants batch in 0.2 m³ steps. Rounding a full cubic metre above what you need is a false saving: returned concrete is typically charged at around $350/m³ ex GST.

Footing Estimator: Enter Your Engineered Sizes

Enter the footing sizes from the drawing. The estimator works out the order volume and an indicative delivered price using the same Sydney small-load rates as our small-load price table. Then enter your address to see live supplier prices for that exact volume and grade.

Footing estimator

Enter the footing sizes from your engineer's drawing

Footing type
Grade on the drawing
Waste allowance

Net volume

2.88 m³

Order

3.2 m³

Indicative delivered

$1,392

Effective rate

$435/m³

Small load. A short-load fee applies below 4 m³, so check the delivered price, not the headline rate. Indicative Sydney price ex GST: $1,232 concrete, $110 cartage, $50 short-load fee. Excludes pump hire, waiting time and Saturday surcharges.

Get live small-load prices for 3.2 m³ of N32

For other shapes, such as square pad footings or a slab behind the wall, use the full concrete volume calculator.

What Grade and Mix for Retaining Wall Footings?

A retaining wall footing holds back soil and water, so it is a structural element. Under the NSW exempt development rules, a retaining wall needs no approval only if it is no more than 600 mm high, at least 1 m from any boundary and meets the other listed conditions. Bigger walls need complying development or a DA, and most need an engineer's design. That design is usually based on AS 4678 Earth-retaining structures and AS 3600 for the concrete itself. Block walls also follow the Concrete Masonry Association of Australia retaining wall design manuals.

Order what the drawing says

If the drawing says N32, don't order N25 to save $30/m³. A certifier can reject the footing, and on a 3 m³ pour the saving is about $90. If there is no drawing and the wall is over 600 mm, get one before you order concrete.

GradeWhere it is usually specifiedSydney material price (ex GST)
N25Low garden walls and sleeper-wall post footings$340–370/m³
N32Engineered block walls, boundary walls and footings in wet or exposed ground$370–400/m³
N40Aggressive soils, coastal exposure or heavily loaded walls$400–440/m³

On a 3 m³ footing, stepping up from N25 to N32 adds only about $90 of material. The grade is rarely where the money goes on a small retaining wall pour. Getting it wrong can mean a failed inspection.

What to Tell the Plant When You Order

  • Grade: N25, N32 or N40, exactly as drawn. Check for an exposure classification note (for example B1 or B2) as well.
  • Slump: 80 mm is common for chute-placed footings. Ask for 100 mm if a line pump is placing it. Never add water on site to make it flow; see why adding water weakens concrete.
  • Aggregate: 20 mm for most footings. Use 10 mm only if the pump or the engineer requires it.
  • Volume and timing: the rounded order quantity, and a delivery time after the steel inspection is signed off.
  • Access notes: street width, driveway slope, overhead wires and distance from the truck to the trench.

The engineer also sets reinforcement, bar laps and cover, which is the concrete between the steel and the ground. Footings cast straight against soil need more cover than formed concrete, so bar chairs must hold the cage at the height shown on the drawing. Starter bars for a block wall must be set in the footing pour. They can't be added afterwards.

Worked Examples With Sydney Pricing

Example 1: 12 m Besser block boundary wall

An engineer specifies a 1.2 m high block wall on a strip footing 600 mm wide × 400 mm deep, N32, with starter bars at 400 mm centres. The wall runs 12 m along the rear boundary of a sloping block in Baulkham Hills.

  1. Net volume: 12 × 0.6 × 0.4 = 2.88 m³
  2. Add 10% waste: 3.17 m³, then round up to 3.2 m³
  3. Concrete: 3.2 m³ × $385/m³ (N32 mid-range) = $1,232
  4. Cartage $110 + short-load fee $50
  5. Indicative delivered: $1,392 ex GST (about $435/m³)

The trench sits 18 m behind the kerb, past the house. A chute reaches about 3–4 m, so this pour needs a line pump. On a typical Sydney line pump job that adds $500–1,000, which is more than a third of the total. Book the pump and the concrete for the same time slot.

Example 2: sleeper wall on 12 steel posts

A 900 mm sleeper wall in a Sutherland Shire backyard has 12 steel posts set in 450 mm diameter piers, 900 mm deep, in N25.

  1. Per pier: π × 0.225² × 0.9 = 0.143 m³
  2. 12 piers: 1.72 m³. Add 10%: 1.89 m³, round up to 2.0 m³
  3. Concrete: 2.0 m³ × $355/m³ = $710
  4. Cartage $110 + short-load fee $100
  5. Indicative delivered: $920 ex GST ($460/m³)

Bagged concrete would need about 210 × 20 kg bags for the same volume. At $8–12 a bag, that is $1,680–2,520 before labour, so ready-mix is cheaper and more consistent from about 0.4 m³ upwards. See ready-mix vs bagged concrete for the full comparison.

Standard Truck, Mini-Mix, Pump or Barrow?

Retaining walls are one of the most access-sensitive small pours. The wall is often at the back of the block or on the low side of a slope, and spoil from the excavation may be stockpiled where a truck would stand. Decide the delivery method before you book.

Site situationLikely methodWhat to check
Front-yard wall, truck can stand within 3–4 mStandard agitator, chute pourKerb and footpath clear, truck level
Narrow street, steep or tight drivewayMini-mix truckWidth, overhead clearance, turning room
Rear-yard trench, 1–2 m³, short flat pathBarrow crewTwo or three barrows, planks over soft ground
Rear-yard or uphill trench, 2 m³ plusLine pumpHose route, pump standing room, 100 mm slump

Unloading time matters on small loads. Plants typically allow a 20–30 minute unloading window, and waiting time after that runs about $2–5 per minute. Barrowing 3 m³ up a slope can easily exceed that window. Use the mini-mix access checklist and pump guide if you are unsure.

Retaining Wall Footing Pour-Day Checklist

  1. Get the steel and trench inspected by the engineer or certifier, then book the concrete. Don't book first and hope the inspection passes.
  2. Pump out any water in the trench and remove loose soil from the base. Rain can collapse sandy trench walls overnight.
  3. Check bar chairs, laps and starter bar positions against the drawing.
  4. Set the ag pipe and drainage aggregate behind the wall to the drawing. The footing is only one part of the wall.
  5. Have the crew, vibrator or rodding tools, and screed ready before the truck arrives. See what to expect on delivery day.
  6. Keep the footing damp while it cures. Concrete typically reaches around two-thirds of its 28-day strength after 7 days of moist curing (see the CCAA curing guidance), so confirm with the engineer before laying blocks or backfilling.

Core-filling a block wall is a separate, later pour. Suppliers allow about 0.8 m³ of concrete per 100 × 200-series blocks. At 12.5 blocks per m², that is roughly 0.1 m³ per m² of wall face. That is often a second small load, and usually a line pump job with a 10 mm aggregate mix. Check the block manufacturer's figure and the engineer's core-fill specification before ordering.

Frequently Asked Questions

How much concrete do I need for a retaining wall footing?
Multiply length × width × depth in metres, then add 10%. A 12 m strip footing 600 mm wide and 400 mm deep needs 2.88 m³ net, so order 3.2 m³.
What MPa concrete is used for retaining wall footings?
Use the grade on the engineer's drawing. Residential retaining wall footings in Sydney are commonly specified as N25 or N32, with N40 for aggressive soils, coastal exposure or heavier walls.
Can I use bagged concrete for a retaining wall footing?
Only for very small pours under about 0.4 m³. A 1 m³ footing needs roughly 105 × 20 kg bags, and a site mix may not reliably reach the specified grade.
Do I need an engineer for a retaining wall in NSW?
In NSW, a wall is exempt only if it is 600 mm or lower and at least 1 m from the boundary. Anything bigger needs approval and usually an engineer's design.
Do I need a pump for a retaining wall footing?
Only if the truck cannot get within about 3–4 m of the trench. Rear-yard walls often need a line pump, typically $500–1,000 in Sydney, or a barrow crew for small loads.
Can I pour the footing and core-fill the blocks together?
Usually not. The footing is poured first around starter bars. Core-fill follows once blocks are laid, often with a 10 mm aggregate mix and a line pump.
What does 3 m³ of N32 cost delivered in Sydney?
Roughly $1,315 ex GST: about $1,155 concrete at $385/m³, $110 cartage and a $50 short-load fee. Pump hire and waiting time are extra.

Ready to order concrete in Sydney?