Concrete Delivery Site Access: Safety Checklist for Builders 2026

A concrete truck needs at least 3\u202Fm of clear road width to access your site safely. For pump setups, maintain 600\u202Fmm clearance between two trucks. Never discharge within 0.9\u202Fm of power lines. A Hi-Vis spotter is required whenever the truck reverses.

Foucauld Dalle, Founder of MixHubUpdated 3 April 2026

Road & Access Requirements

Before you book a concrete delivery, confirm that a fully loaded agitator truck can reach your pour location without obstruction. Based on Boral Australian Concrete Guide (2023 Edition 2.1), Chapter 9, the minimum requirements are:

  • Minimum road width: 3 metres clear of any building materials or debris
  • Extra width is needed for turns — access roads with bends require significantly more room
  • Consider the turning radius of a fully loaded agitator truck (~15 m wheelbase)
RequirementMinimum standardNotes
Road width3.0 m clearClear of debris and materials
Road surfaceFirm, compactedNo soft, boggy, or uneven ground
GradientMax 10% (1:10)Steeper grades require special arrangements
Overhead clearance4.0 mFor agitator drum in raised position
Bridge load ratingCheck with councilAgitator trucks = 30–40 tonne GVM
Turning radiusAllow 15 mFor 8 m3 agitator truck

Before delivery day, walk the access route yourself. Concrete trucks cannot reverse long distances or turn in tight spaces. Problems on delivery day cost $200–400 in waiting charges.

Power Line Clearances

Overhead power lines are the most dangerous hazard for concrete trucks and concrete pump booms. The drum raised for discharge and pump boom arms extend far above ground level.

Line voltageMinimum approach distanceCommon locations
Up to 33,000V0.9 mDomestic street power lines
33,000–132,000V3.0 mSub-transmission lines (suburban)
132,000–330,000V6.0 mTransmission lines
Above 330,000V8.0 mHigh-voltage transmission

No Go Zone Rules

  • No vehicles driving under power lines
  • No trucks discharging while parked under power lines
  • No vehicles or personnel under lines connecting a domestic house to the mains
  • For all other activities near lines: minimum separation distance increases to 3 metres

Source: WorkCover NSW / Boral Australian Concrete Guide (2023 Edition 2.1), Ch 9.

Open Trenches & Excavations

Any part of the truck must stay a minimum distance from open trenches. The rule from Boral Australian Concrete Guide, Chapter 9: trench depth + 1 metre.

  • Trench 500 mm deep → truck must stay 1,500 mm (1.5 m) away
  • Trench 1 m deep → truck must stay 2 m away
  • Trench 1.5 m deep → truck must stay 2.5 m away
Trench depthMinimum truck clearance
250 mm1,250 mm (1.25 m)
500 mm1,500 mm (1.5 m)
750 mm1,750 mm (1.75 m)
1,000 mm2,000 mm (2.0 m)
1,500 mm2,500 mm (2.5 m)

If trenches are close to the pour area, schedule them to be filled and compacted before concrete delivery. Alternatively, use a concrete pump to reach over the trench.

Concrete Pump Setup

When a concrete pump is used, the pump truck and agitator trucks must position precisely. The CCAA Concrete Pump Delivery Industry Guidelines (2014), Page 15 specifies 600 mm as the minimum clearance between trucks and between any truck and a stationary object.

Pump Setup: Top-Down Schematic

STATIONARYOBJECTSTATIONARYOBJECTTRUCK 1→ approachingPUMPMINIMUM 600mmTRUCK 2← approaching

Top-down schematic. Yellow hatched zones indicate stationary objects (barriers, walls, equipment). Trucks must maintain 600 mm clearance from each other and from all stationary objects.

Key Pump Area Requirements
  1. 1Reasonably level, solid and free of obstructions
  2. 2Clear of excavations, trenches or holes
  3. 3Clear of inadequately compacted or soft ground
  4. 4Clear of cellars, basements, pits or back-filled ground
  5. 5Emergency stop must be visible to driver and crew

Source: Boral Australian Concrete Guide (2023), Ch 9. CCAA Concrete Pump Delivery Industry Guidelines (2014), Page 15.

PPE Requirements for Pump Operations

Per Boral Australian Concrete Guide, Chapter 9, all pump operators must wear:

  • Safety helmet
  • Safety glasses
  • Ear protection
  • Hi-Vis vest
  • Work gloves
  • Steel-capped boots

Never stand between a reversing truck and the pump or stationary objects. The primary chute on concrete trucks should only be moved when the truck is stationary.

Spotter Requirements

Per Boral Australian Concrete Guide, Chapter 9, a spotter must be provided by the customer whenever the truck reverses on site.

  • Spotter must be wearing Hi-Vis clothing
  • Spotter must be at a safe distance from the truck and visible to the driver at all times
  • Drivers cannot be used as their own spotter

Traffic control (barriers, cones) is required when:

  • Truck faces oncoming traffic while discharging
  • Truck discharges on or near a main road or hazardous position

Spotter Checklist

Spotter arranged for all reversing movements
Spotter has Hi-Vis vest and is briefed on signals
Traffic management plan in place for roadside pours
Pedestrian access maintained (alternative footpath if truck blocks footpath)

Environmental Requirements

Concrete washdown water is an environmental hazard. From Boral Australian Concrete Guide, Chapter 9:

  • Drivers cannot wash truck chutes onto the street (stormwater contamination)
  • Customer must provide a skip or alternative for chute washdown waste
  • If the truck drags contaminated material off-site, the driver has the right to refuse entry
  • Customer must provide a wheel wash or pressure washer if the truck will carry mud off the site

Pre-Pour Site Checklist

Use this checklist the day before your concrete delivery. Walk the full route the truck will take from the street to the pour location.

Access

Access road is 3 m wide and clear of debris
Surface is firm and can support 30–40 tonne truck
Overhead clearance of 4 m confirmed
Bridge/culvert capacity confirmed if applicable
Gate/entry width measured and confirmed

Power lines

All overhead power lines identified
Minimum clearance confirmed for each line voltage
Pump boom radius mapped vs power line locations

Safety

Hi-Vis spotter arranged for reversing
Traffic management plan in place (if road pour)
All non-essential personnel away from pour zone
No open trenches within trench-depth + 1 m of truck path

Environmental

Skip arranged for chute washdown
Wheel wash or hose available if truck exits to public road
Stormwater drains protected from washdown

Source: Boral Australian Concrete Guide (2023 Edition 2.1), Chapter 9. WorkCover NSW Work Near Overhead Power Lines Code of Practice 2006. CCAA Concrete Pump Delivery Industry Guidelines (2014).

Frequently Asked Questions

How wide does a road need to be for a concrete truck?
A concrete truck needs at least 3 metres of clear width, free of debris and materials. Allow extra width for any turns. For pump trucks, 4 metres is recommended.
Do I need a spotter for concrete delivery?
Yes. A Hi-Vis spotter is required whenever the truck reverses. The spotter must be visible to the driver and positioned away from the vehicle's path. Drivers cannot act as their own spotter.
How close can a concrete truck get to power lines?
For domestic street power lines (up to 33,000V), the minimum approach distance is 0.9 m. For sub-transmission lines (33,000–132,000V), it's 3.0 m. Trucks and pump booms must stay outside these zones.
Can a concrete truck go over a trench?
No. Truck must stay at least ‘trench depth + 1 metre' away from open trenches. A 1 m deep trench requires 2 m clearance. Fill and compact trenches before delivery, or use a pump to reach over them.
Who is responsible for site access?
The customer is responsible for providing safe access for the concrete truck. This includes clear roads, spotter provision, and traffic management. If the driver deems the site unsafe, they can refuse delivery.
How close can a concrete pump boom get to power lines?
The same clearance rules apply to pump booms as to trucks. For domestic lines (up to 33kV): 0.9 m. The pump boom can swing without warning — map its maximum radius before positioning the pump.
What happens if the concrete truck can't access my site?
The supplier charges a standby fee ($200–400/hr) if the truck cannot discharge due to access issues. If the truck must leave without discharging, you may be charged for the full load.

Ready to order concrete in Sydney?